Nearly 30 hectares of sloping grazing land is being turned into a series of evaporative terraces, ending in storage dam, that will be filled with toxic waste water from the mine. This water will evaporate, leaving behind solids in the terraces for future generations to curse us about.
So much for intergenerational equity and the precautionary principle and all that other guff.
But before all of that happens, the terraces will be full of water. They are required to always be wet by the conditions of the VCAT decision handed down in April.
Now when you have multiple bodies of water arranged on a hill, and the sun passes overhead...
Here's a big hole full of water. Just one. And it's only a little big hole, really. All of that land in the background and more on either side will soon be turned into bigger holes full of water.
So, questions for the regulators - any of you will do.
Whoever deals with light pollution.
At what times of the day and at what times of the year will the sun
reflect off the surface of these terraces and into the eyes of residents
on neighbouring properties thereby adversely affecting their amenity through the imposition of blinding light?
What about the impacts on stock?
On wildlife?
Lighting the way along the major Mitchell Trail!
Has anybody done any calculations? Anybody even considered this stuff?
Anybody?
This is a pro-regulation blog. We are not anti-mining. This is not an anti-Mandalay Resources blog.
Wednesday, 26 November 2014
Response from Ms Prue Mansfield
On 25 November, we received the following letter from Ms Prue Mansfield in response to our letter of 19 November.
We also asked to be provided with a copy of the EPA-Appointed Environmental Auditor's Certificate.
Not forthcoming.
Total evasion.
We ask here once more for a copy of that Certificate as well as a copy of the Emerson Dispersive Test and a copy of the geotechnical testing performed on the clay in Lot 2 that is supposed, as per Condition 14 of the Permit, to be in Council's possession prior to works commencing there.
How Ms Mansfield could even think, let alone "believe" that she had "previously answered the other questions" we had raised actually beggars belief. We have never communicated before this exchange.
She has ignored all and any questions regarding dust, noise, vapour, toxic water, dangerous trucks, pollution, smell, the Precautionary Principle, adverse amenity and so much more.
Total evasion.
Works commenced on Lot 1 a week prior to those on Lot 2. No notice was provided for the commencement of works on Lot 1 which was not at that time on the Permit. This oversight was utilised by the DSDBI and EPA to allow Lot 1 preparatory works to commence prior to those on Lot 2 without the required monitoring. The conditions for Lot 1 from the VCAT decision are the same as those for Lot 2. Thus, the VCAT conditions were contravened. It may be a clerical error, but what is that indicative of?
(This should not be a surprise. The original permit application situated the Splitters Creek Facility on Cochranes Rd, Costerfield, rather than the South Costerfield-Graytown Road.)
At no stage does Ms Mansfield address the incremental expansion of the mine or even suggest that it is under consideration or has been addressed by Council.
Not forthcoming.
Total evasion.
We ask here once more for a copy of that Certificate as well as a copy of the Emerson Dispersive Test and a copy of the geotechnical testing performed on the clay in Lot 2 that is supposed, as per Condition 14 of the Permit, to be in Council's possession prior to works commencing there.
We also ask Ms Mansfield to provide us with a definition of a "rehabilitated pit". The Brunswick Tailings Dam has not been rehabilitated. If it had, there would be trees on top and no room for stormwater runoff to be stored.
COGB Performance = Massive Fail
A little searching around the Interwebs revealed that the City of Greater Bendigo has already been treated to the power of the meme...
Here's what others have had to say about this incompetent bunch:
Here's what others have had to say about this incompetent bunch:
Tuesday, 25 November 2014
A New Herbicide Courtesy DSDBI and EPA
Took a drive along the South Costerfield-Graytown Road on 23 November, 2014. Wondering if the treated mine water that is being blended with stormwater runoff stored in the Brunswick Tailings Dam and is then allowed by the Environmental (ahem) Protection Authority to be sprayed along the road and roadsides - and the forest - is having any impact on the vegetation.
This is contaminated water from the mine that is being sprayed along the road in order to suppress the dust caused by the trucks carrying water to suppress dust (!).
It was a dry day. Mid to high 20s. Light wind from the north. Forty-six millimetres of rain had fallen five days before. Nothing in the meantime.
When the trucks spray the toxic waste water as these below are doing, not only does it run into the table drains and flow into farming properties...
...it also kills the vegetation.
This is excellent news in one sense, as it would appear as if the Department of State Development, Business and Innovation has actually found an effective control method for the pest, Chinese Scrub (Biddy bush; Sifton bush; cassinia arcuata).
Just spray heavy metal-contaminated water on the stuff! Easy! That's Innovation, right there!
With just two or three weeks of toxic heavy metal watering, Chinese Scrub can be a thing of the past!
This picture...
...was taken looking back up the road. Look at the dying scrub on the left above.
This picture was taken from a little further down the road. It's like this most of the way along.
The scrub is dying back where it is being sprayed along the roadside. The vegetation further from the road is doing fine.
Excellent news in a sense... but only in one sense...
Because the toxic heavy metal-laden water is also killing the native flora. Like this small wattle.
"Unfortunately" there are plenty of stretches of Chinese Scrub that don't receive the privilege of this DSDB Innovation. They act as our 'control' . See how the stuff thrives when you don't spray toxic water on it...
Same day, 1 km away across the creek.
Letter to the City of Greater Bendigo Council - Vile Water, Vapour and Poor Quality Clay
On the 16 November, Costerfield farmer Mr Gilbert Cochrane wrote the following letter to the City of Greater Bendigo Council.
He is still waiting for an acknowledgement or reply.
16 November, 2014.
Gilbert J. Cochrane
xx xxxx Rd,
Heathcote, 3523; also
Wattle Grove, Cochranes Rd,
Costerfield, 3523.
xx xxxx Rd,
Heathcote, 3523; also
Wattle Grove, Cochranes Rd,
Costerfield, 3523.
To the Mayor and Councillors of the City of Greater Bendigo
Re: South
Costerfield-Graytown dust suppression with mine water
Dear Councillor
We are absolutely disgusted with the operational procedures
currently on display with regards to the construction of the Splitters Creek Evaporative
Facility of Mandalay Resources in Costerfield. It is obvious to anyone who
bothers to take the time to visit Costerfield that what is taking place is the
dumping of the toxic waste water on the South Costerfield Graytown Rd.
On 11 November, 2014, the smell of this water was so vile as
to make one nauseous. So much so that my brothers and I were forced to leave our
property. A vapour was visibly rising from the sprayed road. With summer
approaching, the situation will further deteriorate. Why does your council
refuse to take any action in this regard?
On 14 November, 2014, water tankers were dumping so much of
this material on the abovementioned road that it was running down the table
drain and entering our property and that of our neighbours. I have written to
you previously about this toxic water.
Why will your Council not admit there is a problem and confront
it? Immediate action is imperative.
We are also concerned at the amount of water apparently being
recovered from the top end dam on Lot 1 Splitters Creek. We owned this
allotment and built this dam. Its capacity was 1.5 ML at best. Would your
council please question Mandalay as to whether they are using this dam as a
transfer dam, e.g., carting mine water to and using such in their construction
on Lot 2?
It is vital that you take action immediately. The poor
quality of the clay in this dam meant that it leaked almost continuously.
Consultation with the local community would have informed the Council Planning
Department of this fact. Does Council know of any actions being taken to
monitor for such leakage or to mitigate any environmental impact that may result?
Unless you take action you will leave us no alternative but to have this waste
water and the road privately tested.
I also request that all of the vehicles carrying this water
be tested for heavy metal contamination before any further spraying of this
road is permitted, as it forms part of our properties’ water catchment. Many of
these vehicles were used to transport toxic waste from the mine site at
Costerfield to the Heathcote Pit.
Councillors, what has occurred and what is continuing to
occur here is not acceptable.
Sincerely
G. J. Cochrane
Dip. S.E. Asian Studies
BA (Hons.) Political Science
MA Law and Legal Sudies (Latrobe)
BA (Hons.) Political Science
MA Law and Legal Sudies (Latrobe)
For and on behalf of the Cochrane family and
Wappentake Valley Community
Pollution: Now You See It! Now You Don't!
The solution to pollution is NOT dilution!
Took a drive along the road on 23 November, 2014. We were looking to see if the contaminated water from the mine that is being sprayed along the road by trucks in order to suppress the dust caused by the trucks carrying water to suppress dust (!) was having any impact on the native bushland. The Crown Land.
The pictures of our discoveries regarding threats to flora from the treated water blended with stormwater runoff from the mine that has been stored in the Brunswick Tailings Dam and allowed to be sprayed over the roads and trees by the Environmental - get this! - Protection Authority can be seen here.
It was a dry day. Mid to high 20s. Light wind from the north. Forty-six millimetres of rain fell five days before. Nothing since.
Driving back home, this body of water flashed in our eyes like a mirror.
We are not saying that this is the treated water from the mine that has been mixed with stormwater from the Brunswick Tailings Dam. Not at all. But there is a heck of a lot of it and it looks like it's come from trucks. And it's not really good enough is it?
Now you see it!
Oily, vile water on the roadside. What is it? Lots of it. Thirty or so metres.
So we went for another drive along the road on 25 November, 2014.
Now you don't!
All washed away, eventually into the creek!
Well maybe not all...
Took a drive along the road on 23 November, 2014. We were looking to see if the contaminated water from the mine that is being sprayed along the road by trucks in order to suppress the dust caused by the trucks carrying water to suppress dust (!) was having any impact on the native bushland. The Crown Land.
The pictures of our discoveries regarding threats to flora from the treated water blended with stormwater runoff from the mine that has been stored in the Brunswick Tailings Dam and allowed to be sprayed over the roads and trees by the Environmental - get this! - Protection Authority can be seen here.
It was a dry day. Mid to high 20s. Light wind from the north. Forty-six millimetres of rain fell five days before. Nothing since.
Driving back home, this body of water flashed in our eyes like a mirror.
We are not saying that this is the treated water from the mine that has been mixed with stormwater from the Brunswick Tailings Dam. Not at all. But there is a heck of a lot of it and it looks like it's come from trucks. And it's not really good enough is it?
Now you see it!
Oily, vile water on the roadside. What is it? Lots of it. Thirty or so metres.
It flowed under and then back up.
It soaked the channel. Dug a little hole.
So we went for another drive along the road on 25 November, 2014.
Now you don't!
All washed away, eventually into the creek!
Well maybe not all...
The solution to pollution is dilution, eh?
Thanks for keeping on top of it all EPA-Appointed Environmental Auditor!
The Council of the City of Greater Arrogance
On 24 November, 2014, Ms Pamela King sent the following email to the City of Bendigo Council:
From: Colin Leask [mailto:]
Sent: Monday, 24 November 2014 12:50 PM
To: 'p.mansfield@Bendigo.vic.gov.au'; 'Clare Malcolm'; 'p.cox@bendigocouncillors.org.au'; 'Mark Weragoda'; 'Margaret Mcafee'; j.williams@bendigocouncillors.org.au; 'r.fyffe@bendigocouncillors.org.au'; 'Lisa.Chesters.MP@aph.gov.au'; 'Ian Magee'; 'Andrew Helps'; 'Neil Harris'; 'Graham Connell'
Sent: Monday, 24 November 2014 12:50 PM
To: 'p.mansfield@Bendigo.vic.gov.au'; 'Clare Malcolm'; 'p.cox@bendigocouncillors.org.au'; 'Mark Weragoda'; 'Margaret Mcafee'; j.williams@bendigocouncillors.org.au; 'r.fyffe@bendigocouncillors.org.au'; 'Lisa.Chesters.MP@aph.gov.au'; 'Ian Magee'; 'Andrew Helps'; 'Neil Harris'; 'Graham Connell'
Subject: Splitters Creek Evaporation Facility
To whom it may concern, which is obviously nobody because
nobody ever replies.
The noise is way over the approved 46 plus 10 for
construction dB(A). But nothing is done about it even though we keep
complaining to EPA. We have a hand held monitor, so we are not guessing. It is
not acceptable that Mandalay come along around 12 midday to do the noise
monitoring when the machines or the majority of them have gone back
up to the work site. The noise bounces off the water on the dams and comes
straight up into our house. But nobody knows this as NOBODY ENGAGES
with Colin and Pam at all. The dust that is currently blowing off the work site
on Lot 1 over the road and then down the valley. But what’s the point of
saying anything because then they will just bring the water trucks back in from
the mine and pour contaminated mine water all over the road and the roads they
have made all over Lot 1.
Just met your Ray Chalkley [CoGB Compliance officer]. He was sitting in a
council ute blocking the road, Colin asked him to move and his reply was can,t
you go around. And actually he is not allowed to block the road. He then went
on to inflame the situation by telling Colin he was nothing but a angry little
man, who had a lot of anger in him. I kept telling your employee not to push
the subject, Colin walked away.
City of Greater Bendigo you are completely heartless.
The stress and anxiety you have allowed US to be put
under is completely unacceptable. Please keep the arrogance and rudeness of
your Mr Chalkleys under control. I expect an apology.
Regards
Pamela King
***
Even Bendigo City Council officers are not allowed to block a public road with their cars...
And then the rudeness and the insults... what about that Council? There is a Code of Conduct unless we are very much mistaken.
3.17 Personal Conduct
Staff will treat all people with courtesy and respect, recognising that there are legitimate differences in opinions, race, culture, religion, language, gender and abilities. This includes:
- Treating members of the community with dignity and ensuring that neither offence nor embarrassment are caused.
[...]
- Exercising reasonable care and diligence in performing their functions
- Complying with all relevant laws, be they Federal, State or Local Laws.
It appears that a breach of the Code of Conduct was achieved with Mr Chalkley's insulting behaviour and personal remarks directed at Mr Leask.
Further breaches would appear to have occurred with the parking of a Council car across a public road. That's not legal. Even for a CoGB Officer.
It would appear that the City of Greater Bendigo is attempting to bait the residents of Costerfield into reactions that they would regret.
And so out came Mr Chalkley...
...because he's obviously the Master...
Wednesday, 19 November 2014
Oh, and It Rains in Costerfield, Too! Catch Up!
When it rains in Costerfield, it pours.
Forty-six millimetres of rain and work has ceased at Splitters Creek. Farmers take note of rainfall. Of weather generally.
Mr Leask and Ms King advised the VCAT Members that Lot 2 is a catchment that provided 70% of their water for their home dam through run off. We don't reckon anyone but the Members believed them at the time.
A great big hole has been dug. Presumably it is the terminal dam of the facility. In any case, 46mm of rain has filled the hole and work has ceased.
(The regulators seem to forget about rainfall a lot out here. They forgot to look for it on an early water balance for the mine site.)
Before a DSDBI officer turned up, the water in this dam was about to be channeled out along the road and onto neighbouring properties! Seriously. After dust suppression using contaminated rainwater mixed with treated mine water, it was intended to allow the accumulated contaminants to flow over the road and onto a chemical-free farm.
Forty-six millimetres of rain and work has ceased at Splitters Creek. Farmers take note of rainfall. Of weather generally.
Mr Leask and Ms King advised the VCAT Members that Lot 2 is a catchment that provided 70% of their water for their home dam through run off. We don't reckon anyone but the Members believed them at the time.
A great big hole has been dug. Presumably it is the terminal dam of the facility. In any case, 46mm of rain has filled the hole and work has ceased.
(The regulators seem to forget about rainfall a lot out here. They forgot to look for it on an early water balance for the mine site.)
Before a DSDBI officer turned up, the water in this dam was about to be channeled out along the road and onto neighbouring properties! Seriously. After dust suppression using contaminated rainwater mixed with treated mine water, it was intended to allow the accumulated contaminants to flow over the road and onto a chemical-free farm.
(We'll speak elsewhere of the dispersive nature of these clays that,
according to local knowledge, makes them poor candidates for use in
constructing dams. Dams so constructed, leak. This contaminated water will be
travelling straight down into the basement aquifer anyway, because at the moment that's a hole,
not a dam.)
But then everything seems to involve a game of catch up here. Forgotten, too, was the possibility of a dusty road! And that there was local traffic to be accounted for.
Had to pull over in our 4WD to let him hammer past.
One tanker driver has actually made a report to the police claiming a local resident driving a ute at 40 km/h ran him off the road!
Costerfield residents usually travel at speeds under 40km/h. Because of the dust.
You know, Community and consideration all that.
This road is to be used continuously for at least the next three months while construction proceeds during the dry and dusty - and dare we say windy - summer months. Temperatures regularly over 40 degrees and hot northerly winds.
The road will then be used by mine vehicles to service and operate the evaporation facility upon its completion. Indefinitely.
And so the solution to this long term heavy vehicular use of a country dirt road, used by locals and barely wide enough for a truck and a car to pass is to...
Spray EPA-approved treated mine water that has been blended with collected "putrid" rainwater that "stinks" and has been stored in a "rehabilitated pit" , over the road, into the gutters and onto the vegetation in a Box Iron Bark forest near a rural residential area.
Brilliant!
And what happens on the weekends when the trucks aren't suppressing the dust?
And how long is this going to go on?
Here's how an evaporation pond works:
Here's how an evaporation pond works:
Contaminated water is allowed to evaporate repeatedly over time, leaving behind an ever-increasing amount of solid toxic material.
This is stored 'safely' in a terminal dam.
Here is how dust suppression works on the roads in Costerfield:
Contaminated water is allowed to evaporate repeatedly over time, leaving behind an ever-increasing amount of solid toxic material.
This remains on the road and the roadsides and is blown about by the wind to add to the 'naturally occurring health issue' that the Department of Health is currently investigating.
Can you spot the difference?
The regulators are allowing Costerfield to become one big evaporation facility!
The regulators are allowing Costerfield to become one big evaporation facility!
Has anyone informed the Department of Health?
Reply to Ms Mansfield's Response to our Letter
*** We'd like to thank you all for making this our most popular post of the week ***
*** 170 page views in just two days! ***
*** Thank you for your support! ***
On 10 November, after being excluded from the 6 November Environmental Review Committee meeting because we "are writing a blog attacking the mine", we wrote to the City of Greater Bendigo Council. Of course, the accusation is mistaken.
We are writing a blog attacking the regulators.
On 17 November, we received this unhelpful reply from Ms Prue Mansfield, the City's Director of Planning and Development.
Below is our response. This is some of the lunacy we are talking about.
***
Dear Ms Mansfield,
Thank you for taking the time to respond to my deeply held
concerns regarding the conducting of the ERC Meeting on 6 November.
I note your admission of the inability of Council to even ensure
community attendance at these meetings; even in an observer’s role. It seems
once again, that the regulators and the regulations have allowed any semblance
of responsibility towards and concern for the community to be wrenched from
the very community impacted upon by these mineral extraction operations you
are continuing to permit. And the Chair has no power. We’d already seen that in action.
Thank you for confirming that the decision as to whether or
not an ERC meeting can be “open” or “closed” rests squarely in the lap of the
mining company. Is this a satisfactory state of affairs, Ms Mansfield? Should
anyone have the ability to deny an affected community member the right to
attend such a meeting?
Please do express an opinion so that I and the Costerfield
community may be able to judge whether your and our priorities are the same. Is
this - the effective if misguided steamrolling of community dissent - a situation you would
like to see changed so that the community can have some role in determining its
own future?
Or not?
Are you satisfied at the level of access that the community
has had with regards to its ability to make meaningful contributions in
response to the continued and continuing incremental expansion of this mining
operation over time? Since the community itself is not satisfied and Council claims to
serve the community interests, where does that leave us? You? What processes
are you prepared to set in motion to ensure that concerned community
members are allowed to voice their concerns at the relevant meetings? What do you
think should occur, now?
We have a lot of very serious issues with the way things
have been and are being run, and you, Ms Mansfield, palm us off over here, and
the EPA palms us off over there, but the DSDBI says it’s all your fault, and
then the mine removes us from its property.
We thought we had a ‘whole of government’ response put in
place to address our concerns a few months back, but this seems to have meant
only that we would be wholly ignored by the Government. The departmental jigsaw
puzzle you function within as part of your job, that we, the Public, pay you to
do, is not familiar to us. If
we were facilitated in our ability to raise our concerns to the same level that
the mine is facilitated in disposing of its groundwater, raising its dam walls
and sinking its bores, there may be a few less angry emails banging back and
forth. Some people have the Mining Minister on speed dial; we don’t.
I note the repeated duck-shoving that is taking place here.
Council handballs it to EPA or DSDBI. “Our powers aren’t limitless.” Neither it
would seem are DSDBI’s. Ms Kylie White sent us a letter regarding this project
in which she slaps responsibility for the mess on Council; on you:
In regards to our responsibilities in this matter,
DSDBI monitors and regulates the requirements of licences, work plans and work
plan conditions issued or approved under the MRSDA. Planning permits are issued
and regulated by the relevant planning authority, which in this case is the
City of Greater Bendigo.
DSDBI’s role is to ensure that Mandalay Resources,
as the licence holder, comply with their requirements under the MRSDA and
respond to any concerns from the community about their conduct. The City of
Greater Bendigo is responsible for confirming compliance with the requirements
of the planning permit as the responsible authority and their input is
essential in DSDBI determining if the work plan and conditions are consistent
with the planning permit and appropriate.
The City of Greater Bendigo is responsible for
confirming compliance with the requirements of the planning permit as the
responsible authority and providing appropriate input in determining that the
work plan and conditions are consistent with the planning permit.
Perhaps give Ms White a call and decide between the both of you exactly what it is each of you is
prepared to do on our behalf to stop the regulations from allowing this mining company’s permitted activities
from continuing to ride roughshod over the Costerfield community. Balance. The
mine has been given the power to exclude the community from ERC meetings
because it is their property. But I don’t have the power to keep mining off my
land. Do I?
I note once again the lack of community consultation in this
whole debacle. Residents received no notice from Council that works were
commencing. The Work Plan was quickly stamped and three weeks later unmonitored
works commenced on Lot 2. Work had already commenced on Lot 1 a week prior to
that. Between June, when the permit was completed, and October, when the Work
Plan was signed, no preparatory work was performed on properties around the site. No Council
representative contacted the residents at any stage to find out if they had any
concerns regarding the upcoming development; whether they were satisfied with
the process thus far; what assistance they may need as the project continued;
who they could call to have any concerns addressed. This was a development that
had been treated so seriously by the residents that they had taken Council to
VCAT.
We would have told you about the need to seal the road. Remember, Lot 2 is five kilometres from the
mine site and lies along a dirt road.
Seriously. Did absolutely no one think about the road? The
roads are dusty in Costerfield. There will be a need to cart water along the
South Costerfield-Graytown Road for the next three months at least while
construction proceeds during summer. And for how long after that? Why is the road not sealed?
When will the road be sealed?
Is this really an
exercise in dust suppression or is it another method to facilitate the mine’s disposal
of the obviously excessive amount of groundwater it is being allowed to remove?
Perhaps you can ask EPA and DSDBI and G-MW on our behalf. Please do get back to us with their reply.
If the water cannot be disposed of by methods other than
‘dust suppression’ on the Costerfield roads, then it would seem Mandalay’s
dewatering allowance of 700ML/year is too great. As the situation stands the mine
is in a better position to deal with its over-apportionment of toxic waste water
than it was when toxic waste water was
allowed to be trucked fifteen kilometres along a main road, a highway and
through the town of Heathcote to the disused Heathcote Pit!
(The Heathcote-Nagambie Road still bears the dangerous scars of the endless parade of water tankers in its potholes and ragged corners. Is Council doing anything about that?)
(The Heathcote-Nagambie Road still bears the dangerous scars of the endless parade of water tankers in its potholes and ragged corners. Is Council doing anything about that?)
The South Costerfield-Graytown Road, on the other hand, is
going to be used by Mandalay Resources for the foreseeable future. Years it
would seem. Is Council satisfied that the spraying of toxic waste water (it has
been stored in something called a ‘rehabilitated pit’ for goodness sake!) onto
the South Costerfield-Graytown Road should continue, day in and day out for the
next… say, five, perhaps ten years?
As you will no doubt be aware the principles underlying an evaporation
facility are that water evaporates and leaves solid toxic contaminants behind in ever-increasing
amounts. So we keep them “safe” in a terminal dam. When this or
similar water is sprayed on the road and forest for three months it also evaporates and leaves solid
toxic contaminants behind in ever-increasing amounts. But in Costerfield these
contaminants get to lie on the road and in the bush and then blow about the district and poison us.
Have you informed the Department of Health about this possible disruption to their testing regime?
Have you informed the Department of Health about this possible disruption to their testing regime?
Do you actually have a plan that addresses this potential
problem? Or are you just winging it again? Or is it the EPA’s problem? EPA says
the water is safe apparently; we say it stinks. Smell… safe or not, that's adverse amenity.
Council has received numerous complaints from residents
regarding noise and dust. And the response? Arrange an
inspection of the site, travel all the way to Costerfield and then neglect to pop
across the road to talk to the very people who have raised the concerns.
Just a little hint. If you want to see whether the mine is
abiding by the conditions of the Permit DON’T call it up and allow it an hour’s
notice to ensure the roads are watered, remind its contracted drivers to slow
down to a cautious speed on the public road and check that the machinery is
operating below acceptable noise and dust levels. We don’t believe anyone is
so naïve as to think that the mine would not do that to ensure compliance, it's only natural; consequently, we don’t exactly know why anyone would not
have followed our hint already…
This is more than a matter of politeness, decency and
fairness, although that should be enough. It is a matter of you doing your jobs
as Public Servants. Of responding to the landowners, ratepayers and
voters of Bendigo as per Council’s policy of Community Consultation. If a
resident calls up and complains, please respond to the resident. It is
patently obvious who is calling the tune here. When the Mayor visited
Costerfield to assess a community complaint regarding work at the site, did he
bother to contact the community? At all?
It is our belief that the Permit still has some importance
here, whether you are going to bother enforcing it or not (“and the usual
result from VCAT is to give a company some time (months) to bring an issue into
compliance” – so let’s not bother at all then, is that what you are saying? A
couple of months of non-compliance is better than the next ten years, isn’t it,
Ms Mansfield?) There is a condition on the Permit that reads:
The use permitted by this permit
must not, in the opinion of the responsible authority, adversely affect the
amenity of the locality by reason of the processes carried on; the transportation of materials, goods
or commodities to or from the subject land; the appearance of any
buildings, works or materials; the emission
of noise, artificial light, vibration, smell, fumes,
smoke, vapour, steam, soot,
ash, dust, waste water, waste products, grit or oil; the
presence of vermin, or otherwise.
Trucks full of waste water barrel dangerously along a public road at breakneck speed. The water they spray is putrid. It stinks. Smell.
Heavy metals. Dust. Waste water. “In the opinion of the responsible authority”
– that’s you guys, not the EPA or
anyone else – does or will the spraying of this vile, putrid water – that
has been sitting in a ‘rehabilitated’ pit leaching toxic materials – about the
roads and roadsides of Costerfield during the dry summer months, adversely
affect our amenity? The dangerous trucks? What do you need to be told to convince you that this is
the case? You say your powers aren't limitless; do you have any powers at all to stop this?
Ms Mansfield, you have claimed responsibility for the
Permit. Why is Lot 1 and the Crown Land not on the Permit? How did that
oversight occur? The VCAT decision specifically names Lot 1 as Subject Land
with regards to the construction of the Evaporation Facility, and yet no
mention is made of “Lot 1 & Lot 2 and the Crown Land between these lots and
the mine site” in the Permit. As a consequence works commenced on Lot 1 in
contravention of the VCAT Decision.
Has a Planning Permit been issued for Lot 1, yet? Will you
make a copy of that available to us please? And can we please also receive a copy of
the EPA-appointed Environmental Auditor’s Certificate? We have asked for this
already but to no avail. Please do not ask us to pay for these documents as Ms
White so patronisingly did. Sheer arrogant evasion from someone who claims her
Department’s “role” is to “respond to any concerns from the community”.
Planning contortions developed to over-facilitate the mining
company’s requirements mean that building a five kilometre poly pipeline
between the mine site and Splitters Creek and pumping water along its length
from one place to another – from one Mining Licence to another – somehow does not constitute the water leaving
the mine site. So, in effect, the mine site has been expanded to incorporate
two separate mining licences, with a plastic pipe full of waste water acting as
a kind of umbilical cord to make the two into one.
How has this occurred without reference to the “cumulative
impacts” noted in the Precautionary Principle which underlies the Rio Declaration and to which Council is a signatory? The mine is no longer just ML4073. It now
encompasses a further Mining Licence, ML5567.
What is your plan for the future development of this mine?
Please do examine the plans for Lot 2 and advise us how they
do NOT indicate that the Splitters Creek Evaporative Facility is likely to be
expanded so as to encompass Lot 1 also. That option is certainly open, is it
not? Ask and ye shall receive seems to be the order of the day. No mining
licence was required to construct this evaporative facility. Does Mandalay
Resources intend mining on this land, too? Council will without doubt
approve any extension since it will examine such development, as it always has
done, in isolation from the rest of the operations, not as an incremental
expansion. “On its merits.” Whatever that may mean.
What is your plan for the future development of this
mine?
How extensive is the intended expansion of this mine? This
is no longer a short term venture. The current mine has been present and has
extended that presence considerably for and over the last decade. It is not
going away. How big have you planned for it to get?
Do you think this
is why Councillor Chapman asked me why I did not approach the mine and sell my
land?
What is your plan for the future development of this
mine?
How big is this mine going to be allowed to get before you
react? You should have some idea because it has been here since 2003 and you
keep on letting it grow. You are examining its expansion, aren’t you?
Please do visit our blog. We think that you
will find the following documented posts very informative. They will also
go some way to indicating to you why we are very angry.
This is what the regulators, you among them, have allowed to
transpire in Costerfield because you won’t address the expansion of the mine
and apply the Precautionary Principle as you are required to do.
Please do also read our Letter
to the Minister II – Best Practice Required post. You will see there that
we are neither anti-mining nor anti-this mine. That is why we wished to attend
the ERC meeting. We have constructive solutions that do not entail closing the
mine, despite what you may suspect. If we are going to have to have a mine we want the best mine you
can make it. And so we want you and your people to do your jobs properly and remember that
you have a duty of care over the people of Costerfield and of Bendigo that
should trump the over-facilitation of mineral extraction. Precautionary.
The people of Costerfield feel they are a little more
important than a couple of holes in the ground. It would be nice to see that you
agreed with us and to receive some assistance in maintaining our community’s
health and well-being. And our ability to have our say.
For now, though, it seems, we must wait another three months
in order to be inevitably excluded from the next ERC Meeting.
Thanks for your offer of support. Oh, that’s right, you
didn’t offer any.
Thanks again for your time, then.
Thanks again for your time, then.
Regards
Steve Blackey
Subscribe to:
Posts (Atom)