This is a pro-regulation blog. We are not anti-mining. This is not an anti-Mandalay Resources blog.

Tuesday, 30 September 2014

Cumulative Impact

Patience Grasshopper...

Under construction. Check back soon!

From
The Precautionary Principle, The Coast and Temwood Holdings by The Hon. Justice Stephen Estcourt, Judge, Supreme Court of Tasmania, delivered at the Australasian Conference of Planning and Environment Courts and Tribunals, Henry Jones Art Hotel, Hobart, 5 - 7 March 2014


As to the first condition precedent, or threshold, to the engagement of the principle, namely "the threat of serious or irreversible environmental damage", Osborn J, after a consideration of Preston CJ's factors pointing to the existence of a threat, adopted the language of the Shirt calculus. His Honour said:
"In my view the statement in another context by Mason J in Wyong Shire Council v Shirt, that a risk though remote may nevertheless be real and not fanciful or far-fetched is apposite here. At 48 his Honour stated that '[a] risk which is not far-fetched or fanciful is real and therefore foreseeable.'" [60]
As to the second of the conditions precedent, namely, that there be "a lack of full scientific certainty", Osborn J noted that, as with the first condition precedent, it was a question of fact, potentially involving complex factors, and he set out Preston CJ's postulation of those factors.[61] He then referred to Preston CJ's summation of the body of theoretical debate as to what is the requisite degree of uncertainty required to trigger application of the principle [62], and concluded, pragmatically:
"In the present case I propose to analyse the evidence on the basis of a standard of substantial uncertainty. Such a standard falls within the ambit of the principle whatever may be its theoretical limits." [Emphasis added.]
Next, from the Telstra case [64], Osborn J noted that if the two conditions precedent were satisfied, then the burden of showing that damage would not occur "effectively shifts to VicForests to show that the threat of environmental damage does not exist or is negligible".
His Honour then [66] helpfully epitomised the pivotal principles to be derived from Preston CJ's exegesis, as follows:
• The precautionary principle permits the taking of preventative measures without having to wait until the reality and seriousness of the threat have been fully known.
• The precautionary principle is not directed to the avoidance of all risks.
• The degree of precaution appropriate will depend on the combined effect of the seriousness of the threat and the degree of uncertainty.
• The margin for error in respect of a particular proposal may be controlled by an adaptive management approach.
• The precautionary principle requires a proportionate response. Measures should not go beyond what is appropriate and necessary in order to achieve the objective in question. The principle requires the avoidance of serious or irreversible damage to the environment wherever practicable. It also requires the assessment of the risk-weighted consequences of optional courses of action.
• A reasonable balance must be struck between the cost burden of the measures and the benefit derived from them.
• The relevant notion of proportionality is however not readily captured by traditional cost benefit analysis.
• The triggering of the precautionary principle does not necessarily preclude the carrying out of a particular land use or development proposal.
• The precautionary principle may also require consideration in the context of other principles of environmentally sustainable development.
Osborn J then proceeded to operationalise the precautionary principle in the case before him, adopting a checklist approach. His Honour said:
"In summary, the application of the precautionary principle to aspects of this case raises the following fundamental issues:
(a) is there a real threat of serious or irreversible damage to the environment?
(b) is it attended by a lack of full scientific certainty (in the sense of material uncertainty)?
(c) if yes to (a) and (b), has VicForests demonstrated the threat is negligible?
(d) is the threat able to be addressed by adaptive management?
(e) is the measure alleged to be required proportionate to the threat in issue?"


Irreversible Damage

Patience Grasshopper...

Under construction. Check back soon!

From
The Precautionary Principle, The Coast and Temwood Holdings by The Hon. Justice Stephen Estcourt, Judge, Supreme Court of Tasmania, delivered at the Australasian Conference of Planning and Environment Courts and Tribunals, Henry Jones Art Hotel, Hobart, 5 - 7 March 2014


As to the first condition precedent, or threshold, to the engagement of the principle, namely "the threat of serious or irreversible environmental damage", Osborn J, after a consideration of Preston CJ's factors pointing to the existence of a threat, adopted the language of the Shirt calculus. His Honour said:
"In my view the statement in another context by Mason J in Wyong Shire Council v Shirt, that a risk though remote may nevertheless be real and not fanciful or far-fetched is apposite here. At 48 his Honour stated that '[a] risk which is not far-fetched or fanciful is real and therefore foreseeable.'" [60]
As to the second of the conditions precedent, namely, that there be "a lack of full scientific certainty", Osborn J noted that, as with the first condition precedent, it was a question of fact, potentially involving complex factors, and he set out Preston CJ's postulation of those factors.[61] He then referred to Preston CJ's summation of the body of theoretical debate as to what is the requisite degree of uncertainty required to trigger application of the principle [62], and concluded, pragmatically:
"In the present case I propose to analyse the evidence on the basis of a standard of substantial uncertainty. Such a standard falls within the ambit of the principle whatever may be its theoretical limits." [Emphasis added.]
Next, from the Telstra case [64], Osborn J noted that if the two conditions precedent were satisfied, then the burden of showing that damage would not occur "effectively shifts to VicForests to show that the threat of environmental damage does not exist or is negligible".
His Honour then [66] helpfully epitomised the pivotal principles to be derived from Preston CJ's exegesis, as follows:
• The precautionary principle permits the taking of preventative measures without having to wait until the reality and seriousness of the threat have been fully known.
• The precautionary principle is not directed to the avoidance of all risks.
• The degree of precaution appropriate will depend on the combined effect of the seriousness of the threat and the degree of uncertainty.
• The margin for error in respect of a particular proposal may be controlled by an adaptive management approach.
• The precautionary principle requires a proportionate response. Measures should not go beyond what is appropriate and necessary in order to achieve the objective in question. The principle requires the avoidance of serious or irreversible damage to the environment wherever practicable. It also requires the assessment of the risk-weighted consequences of optional courses of action.
• A reasonable balance must be struck between the cost burden of the measures and the benefit derived from them.
• The relevant notion of proportionality is however not readily captured by traditional cost benefit analysis.
• The triggering of the precautionary principle does not necessarily preclude the carrying out of a particular land use or development proposal.
• The precautionary principle may also require consideration in the context of other principles of environmentally sustainable development.
Osborn J then proceeded to operationalise the precautionary principle in the case before him, adopting a checklist approach. His Honour said:
"In summary, the application of the precautionary principle to aspects of this case raises the following fundamental issues:
(a) is there a real threat of serious or irreversible damage to the environment?
(b) is it attended by a lack of full scientific certainty (in the sense of material uncertainty)?
(c) if yes to (a) and (b), has VicForests demonstrated the threat is negligible?
(d) is the threat able to be addressed by adaptive management?
(e) is the measure alleged to be required proportionate to the threat in issue?"


Scientific Uncertainty

Patience Grasshopper...

Under construction. Check back soon!

From
The Precautionary Principle, The Coast and Temwood Holdings by The Hon. Justice Stephen Estcourt, Judge, Supreme Court of Tasmania, delivered at the Australasian Conference of Planning and Environment Courts and Tribunals, Henry Jones Art Hotel, Hobart, 5 - 7 March 2014


As to the first condition precedent, or threshold, to the engagement of the principle, namely "the threat of serious or irreversible environmental damage", Osborn J, after a consideration of Preston CJ's factors pointing to the existence of a threat, adopted the language of the Shirt calculus. His Honour said:
"In my view the statement in another context by Mason J in Wyong Shire Council v Shirt, that a risk though remote may nevertheless be real and not fanciful or far-fetched is apposite here. At 48 his Honour stated that '[a] risk which is not far-fetched or fanciful is real and therefore foreseeable.'" [60]
As to the second of the conditions precedent, namely, that there be "a lack of full scientific certainty", Osborn J noted that, as with the first condition precedent, it was a question of fact, potentially involving complex factors, and he set out Preston CJ's postulation of those factors.[61] He then referred to Preston CJ's summation of the body of theoretical debate as to what is the requisite degree of uncertainty required to trigger application of the principle [62], and concluded, pragmatically:
"In the present case I propose to analyse the evidence on the basis of a standard of substantial uncertainty. Such a standard falls within the ambit of the principle whatever may be its theoretical limits." [Emphasis added.]
Next, from the Telstra case [64], Osborn J noted that if the two conditions precedent were satisfied, then the burden of showing that damage would not occur "effectively shifts to VicForests to show that the threat of environmental damage does not exist or is negligible".
His Honour then [66] helpfully epitomised the pivotal principles to be derived from Preston CJ's exegesis, as follows:
• The precautionary principle permits the taking of preventative measures without having to wait until the reality and seriousness of the threat have been fully known.
• The precautionary principle is not directed to the avoidance of all risks.
• The degree of precaution appropriate will depend on the combined effect of the seriousness of the threat and the degree of uncertainty.
• The margin for error in respect of a particular proposal may be controlled by an adaptive management approach.
• The precautionary principle requires a proportionate response. Measures should not go beyond what is appropriate and necessary in order to achieve the objective in question. The principle requires the avoidance of serious or irreversible damage to the environment wherever practicable. It also requires the assessment of the risk-weighted consequences of optional courses of action.
• A reasonable balance must be struck between the cost burden of the measures and the benefit derived from them.
• The relevant notion of proportionality is however not readily captured by traditional cost benefit analysis.
• The triggering of the precautionary principle does not necessarily preclude the carrying out of a particular land use or development proposal.
• The precautionary principle may also require consideration in the context of other principles of environmentally sustainable development.
Osborn J then proceeded to operationalise the precautionary principle in the case before him, adopting a checklist approach. His Honour said:
"In summary, the application of the precautionary principle to aspects of this case raises the following fundamental issues:
(a) is there a real threat of serious or irreversible damage to the environment?
(b) is it attended by a lack of full scientific certainty (in the sense of material uncertainty)?
(c) if yes to (a) and (b), has VicForests demonstrated the threat is negligible?
(d) is the threat able to be addressed by adaptive management?
(e) is the measure alleged to be required proportionate to the threat in issue?"




Tell the Mayor about Rio

On 25 August, 2013, in response to a request from the then-Mayor during her visit to Costerfield Community Hall to provide Councillors with details of the Rio Declaration and the Precautionary Principle we sent the following email...


Dear Lisa,

Let me thank you once again for taking time out from your busy schedule to attend our meeting in Costerfield last night and for graciously allowing us to have our voices heard in this matter. Your presence and availability were and are very much appreciated.

 
You asked me to provide you with details and links regarding the particular aspects of the 1992 Rio Declaration on Environment and Development that we consider to be pertinent to our submissions and statements and to which we feel Council's attention should be drawn. Prior to that though I hope you'll allow me to make a few clarifications so as to lend a little background to our position and to give you an idea of the kind of concerns and attitudes with which you are dealing....
[there follows details of our own properties that are not relevant here.]
                                                                      ****
Regarding the Rio Declaration on Environment and Development 1992 and its relation to our predicament. As you and your fellow Councillors will be aware, local government, as governmental arms of the the Australian state are signatories to the Principles contained within the Declaration. Of particular relevance in the current situation, as in all matters of ecologically sustainable development (ESD) is this statement from the New South Wales Law and Environment Council, which I have italicised in places to emphasise their pertinence and which states explicitly that:

    "Four of the Rio Declaration principles are substantially reflected in subsequent Australian legislation, namely:           

  •  Principle 3. The right to development must be fulfilled so as to equitably meet developmental and environmental needs of present and future generations.
  •  Principle 4. In order to achieve sustainable development, environmental protection shall constitute an integral part of the development process and cannot be considered in isolation from it.
  • Principle 15. In order to protect the environment, the precautionary approach shall be widely applied by States according to their capabilities. Where there are threats of serious or irreversible damage, lack of full scientific certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental degradation.
  • Principle 16. National authorities should endeavour to promote the internalization of environmental costs and the use of economic interests, taking into account the approach that the polluter should, in principle, bear the cost of pollution, with due regard to the public interest and without distorting international trade and investment.

        The central concept of ESD, the integration of environmental protection and development, appeared in Principal 4. Three of the four pillars on which the concept rests- the precautionary principle, the principle of intergenerational and intra-generational equity and the internalisation of environmental costs principle - were embodied in, respectively, Principles 15, 3 and 16. However Principle 16 was heavily qualified."
(The full document is available at http://www.lec.lawlink.nsw.gov.au/agdbasev7wr/_assets/lec/m420301l711805/biscoe_esdnsw.pdf)

And therein lies the crux of the issues to which we wish to draw Council's attention. This is no place to present our own interpretations of the applicability of these considerations to our own situation - that will be done in a forthcoming submission to Council - but it will serve further explication of the matters at hand to refer you and your fellow Councillors to some of the relevant background regarding the application of these principles under Australian Law; especially the 'precautionary principle'. For a thorough but accessible encapsulation of the legal issues I would be hard-pressed to direct your attention to a more succinct summary than the discussion of Telstra Corporation vs Hornsby Shire Council 1996 and other allied cases, and the recommendations of Chief Justice Preston provided in this synopsis of The Precautionary Principal in Australia.  The transcript of Justice Kevin Bell of the Supreme Court of Victoria's 2010 seminar on the issue of "The Precautionary Principle: How do courts use it to protect the environment?" is another informative resource.

                                                               ****
We are reasonable people and we are ready to take into account, and be convinced by, the thoroughly scientific evidence. But this is a process that demands equitability and reciprocity and so the scientific evidence must be convincing and must thoroughly take us into account, too

Please come out and visit us at any time to experience our beautiful land and have a cuppa and a chat. 

Once again thank you very much for providing this opportunity to communicate with you and for listening.

Cheers 

Initial Hydrogeological Investigations



In 2005 the Planning Permit was altered to include the need for the completion of a hydrogeological report into the possible impacts of mine dewatering on the groundwater in the area. This groundwater has served as a stock watering amenity for the farmers in Costerfield for generations. 

The mine was able to subvert this condition with the acquiescence of the regulators by twisting the wording of Permit Condition 24. The so-called report that was eventually presented to the Environmental Review Committee by AGD was, in fact, merely a seven-page letter.

No evidence of the commissioning of a completed initial hydrogeological report has ever been presented by the mine, merely the letter calling for an expression of interest that is transcribed below. A copy is available here.

Dewatering nevertheless (re)commenced and further potential cumulative irreversible environmental damage to the groundwater system was allowed to proceed under the watch of the Responsible Authority.


Who were the regulatory officers who confirmed that the letter calling for an expression of interest from URS was actually a commissioning document? 

On what basis?


 Can we see the commissioning document?

***
Planning Permit 
DM/753/03 – Permit for an Underground Mine
14 January 2004

[Condition] 26. Three (3) bores at locations to be determined by Goulburn-Murray Water in consultation with the Responsible Authority, shall be installed up to one (1) kilometre from the mining site, with two (2) being downstream and at least one (1) being one 1 (km) from the mine site and regular results observed to monitor any impacts of the dewatering on the groundwater levels be reported to the Environmental Review Committee.

There was obviously concern about the impact on groundwater levels from the mine’s dewatering operations. And, of course, there would be. The farmers in the area have been using the groundwater-fed creeks and water holes for over a century to water their stock all year round. The creeks retract into a series of pools and ponds (real ponds: frog live in them) but never completely dry up. Flows cease but the water remains. 

Remained.

ERC Meeting
9 March 2005
4.2 Current Status of Approval Process

Colin Burns stated that the Work Plan Variation had been submitted to DPI and had been referred to various departments and authorities and was very close to the stage where it would be endorsed.

Colin Thornton confirmed that this was the case and that the only outstanding matter related to DSE desire to detailed management plans for offset sites prior to endorsement.

Colin Burns indicated further discussions would be held with DSE and that once endorsement had been received an application for a Planning Permit would be made.
Colin Burns stated that hydrogeological work to produce detailed designs for the groundwater monitoring and seepage detection systems was planned.

Fred Shea suggested there was a government hydrogeological group that could be able to undertake this work. Colin Burns agreed to contact them.
***

Obviously endorsement took place because the Permit acquired a new condition to replace Condition 26 of the previous Permit iteration. And why would it not? This seems like a pretty good condition; one that addresses the issues raised at the ERC meeting very thoroughly.

Planning Permit 
DM/253/2005 – Permit for an Underground Mine
11 August 2005
 ***
And so Colin Burns contacted URS. He explains the process undertaken to get the condition altered. Doesn’t sound like he was too pleased about all the trouble he was having to go to.

6 July 2005
Hydrogeological Investigation
Impact of Mine Dewatering at Costerfield

1. Introduction
AGD Operations Pty Ltd requires the services of a hydrogeological consultant and invites URS Australia Pty Ltd to submit a proposal for the provision of those services.

2. Background
Mining of the Augusta deposit will require mine dewatering and the potential for the lowering of groundwater levels on the supply of water to properties in the area needs to be considered. Consideration of this matter thus far is summarised below.

·        Preliminary investigations into the impact of the mine dewatering on groundwater levels indicate that the zone of impact will extend up to 1500 metres from the mine.

·        There is one registered “bore” within the 1500 metres of the proposed mine that is licensed for groundwater extraction and this bore is I fact a disused mine shaft from which water is no longer extracted.

·        There are no known users of groundwater in the area.

It has been concluded from the above that mine dewatering will not have any detrimental impact on groundwater use, however some concern has been expressed by local landowners in regard to the impact of such dewatering on water sources within their properties.

On several properties in the area water is obtained from “collection points” which are apparently fed by a combination of surface run-off and water that enters the collection point through the ground. Water continues to enter these collection points after surface run-off has ceased and as a result there is a belief amongst property owners that they are fed from groundwater. While there is some evidence, in terms of the water quality and the relative depths of the collection points and the groundwater, that this belief could well be erroneous, the perception remains. In response to these concerns, the City of Greater Bendigo included the following in a Planning Permit relating to the proposal for an underground mine.

Three (3) bores at locations to be determined by Gouburn-Murray Water in consultation with the Responsible Authority, shall be installed up to one (1) kilometre from the mining site, with two (2) being downstream and at least one (1) being one 1 (km) from the mine site and regular results observed to monitor any impacts of the dewatering on the groundwater levels be reported to the Environmental Review Committee.

Subsequent to the grant of this permit AGD decided to vary the proposal to include an open pit mine thus requiring a new Planning Permit. In the course of applying for a new permit AGD pointed out that the above condition was nonsensical and was unlikely to achieve the result required. In response the Council determined that the above condition be replaced with the following:

Prior to the commencement of mine dewatering a qualified hydrogeologist will be commissioned to complete an investigation into the existence of a hydrological connection between the groundwater in the area of the mine and the water collection points utilised on properties in the area as a source of water, the need for a groundwater monitoring program to enable assessment of the impact of the mine dewatering on water supplies and, if such a needs exists, a detailed design of such a program. The hydrogeologist’s report will be provided to Goulburn Murray Water, the Responsible Authority and the Environmental Review Committee and must be to the satisfaction of Goulburn Murray Water and the Responsible Authority.

It is apparent from the foregoing that a hydrogeological study needs to be completed.

***
And one would presumably also say that it is apparent, too, that that study be completed prior to the commencement of mine dewatering. 

It should have been (and in the end obviously was) a pretty simple investigation. Burns was kind enough to provide URS with not only the three pieces of evidence they should deem pertinent, but also the conclusion that could be drawn (“It has been concluded from the above”) from their mere presentation: “that mine dewatering will not have any detrimental impact on groundwater use.” Still, to assuage those “local landowners” and their worries about, perhaps, losing some of the Constitutionally-guaranteed amenity of water that they employ to maintain their stock, the report would have to be done; “needs to be completed”.

He also manages to twist the natural questioning of an uncertainty into something that is somehow inconceivable: “While there is some evidence, in terms of the water quality and the relative depths of the collection points and the groundwater, that this belief could well be erroneous, the perception remains.” Perhaps those naïve landowners are confusing “water that enters the collection point[s] through the ground” with them being “fed from groundwater”.

Obviously the perception remains because there is only “some evidence” that the “belief could well be erroneous”. “Some”, “could well be” – not very convincing stuff. Scientific uncertainty? You aren’t going to change “local landowners’” minds with that sort of vacillation. They’ve been here for generations and reckon they know the land a little better than Burns. Believe it or not, they want evidence before they let you perpetrate irreversible damage to their lands.

And to say that there “are no known users of groundwater in the area” is a blatant lie. As explained above, farmers in the area have used the groundwater-fed creeks and “collection points” for generations. The groundwater was always available and did not need to be accessed via bores.

In any case, at least Burns was clear in his final sentence here as to what had to happen: “It is apparent from the foregoing that a hydrogeological study needs to be completed.” [Emphasis added.]

Here is the first sentence of that Permit condition again. “Prior to the commencement of the mine a qualified hydrogeologist will be commissioned to complete an investigation into the existence of a hydrological connection…” Seems simple enough. Get someone in to do a report so you know what the situation is before you dewater. One would not want to begin possibly destructive actions upon the groundwater system without knowing of the possibility or extent of any hydrological connection. Would one? And one wouldn’t want to possibly compromise the investigation by commencing dewatering before a qualified hydrogeologist had assessed the extant, “baseline” conditions? Would one? That would be like shutting the gate after the horse has bolted, surely. 

Scientific uncertainty irreversible damage, cumulative impacts...

Yet despite the lack of any such report and in total disregard of this condition, the Permit was stamped (see above) by COGB’s Greg Speirs on 11 August, 2005.



***

Now listen in on the 8 March 2006 ERC Meeting where a local resident ERC Member asks about the completion of this initial hydrogeological report:

6.4 Groundwater
6.4.1 Groundwater Levels

Groundwater levels have been monitored at a variety of locations during the pre-production dewatering that occurred during January and February. Results show that the water level at the point of pumping has fallen some 18.5 metres while water levels at all other points have fallen much less (0 to 2 metres).
Colin Thornton observed that the results are only indicative of what has happened during the preliminary stages of dewatering. Colin Burns agreed and indicated that monitoring would be on going.

B** asked why the DPI had approved the commencement of dewatering when the Planning Permit required that a hydrogeological study be completed prior to commencement of dewatering.

Colin Thornton indicated that while DPI was not responsible for enforcing planning permit conditions, they were not aware that any breach of planning permit conditions had occurred.

Colin Burns stated that the Planning Permit requirement had been satisfied since the requirement is that “Prior to the commencement of dewatering a qualified hydrogeologist will be commissioned to complete an investigation….” [Emphasis actually in the original ERC Minutes!] A hydrogeologist has been commissioned and has provided a report, a copy of which has been provided to all ERC members. The fact that the report recommends further work and that such recommendations have been accepted by AGD [!!] does not mean that dewatering should not be commenced prior to the completion of further work. 

Colin Thornton noted that the further work recommended by the hydrologist cannot be conducted unless dewatering is commenced.

Greg Speirs indicated that he did not believe that the commencement of dewatering was breach of the planning permit conditions but that he would review the matter.

It is almost as if someone asked for a sentence that could be used as an example of a breach of the precautionary principle here. 

Compare these two utterances, please:

The fact that the report recommends further work and that such recommendations have been accepted by AGD does not mean that dewatering should not be commenced prior to the completion of further work.

 and

Lack of full scientific certainty should not be used as a reason for postponing a measure to prevent degradation of the environment where there are threats of serious or irreversible damage to the environment

At Costerfield, then, it would seem that lack of full scientific certainty - the fact that "further work" needs to be done - should not be used as an excuse to postpone the continuation of dewatering - dewatering that may pose the threat of serious or irreversible damage to the environment. Whatever the mine might want.

Say hello and good-bye to the precautionary principle at Costerfield!

And, here, we also have two regulators, Speirs and Thornton, facilitating the commencement of mining operations in contravention of Planning Permit condition 24 by acceding to the tortuous semantics of the mine’s representative, Colin Burns. The Goulburn Broken Catchment Management Authority representative, Gordon O’Brien, remained silent. No Goulburn-Murray Water Representative was in attendance or offered an Apology.

And here we also learn that dewatering had already commenced in January and February

So the horse had bolted. 

Would it really be the case that Council, in order to assess the impact of the mine “prior to …dewatering” would call for the mere commissioning of a hydrogeologist? Indeed there appear to be at least two, and probably three tasks that need completing

to complete an investigation into the existence of a hydrological connection between the groundwater in the area of the mine and the water collection points utilised on properties in the area as a source of water, the need for a groundwater monitoring program to enable assessment of the impact of the mine dewatering on water supplies and, if such a needs exists, a detailed design of such a program.

Surely it was intended that the results of this investigation be known before dewatering commenced, no? That would be the point of the “assessment”. Did Council intend that the detailed design of a groundwater monitoring program be provided prior to the completion of the very investigations that would inform that program? And it would be irresponsible of the Responsible Authority to give the greenlight to mine dewatering before the results of any investigation were in, thereby possibly causing irreversible damage to a groundwater system they knew little about, surely.

“commissioned to complete”; “It is apparent from the foregoing that a hydrogeological study needs to be completed.”

But the mine had already been allowed to dewater in January and February – producing a drop in groundwater in places of up to 18.5 metres – “Colin Thornton observed that the results [i.e., the drop in groundwater levels!] are only indicative of what has happened during the preliminary stages of dewatering” [!!!] – and was then allowed to proceed with its dewatering and the expansion of its area of impact, merely by alleging the commissioning of a study.

There is, of course, the mention here of the “report” produced by the allegedly commissioned hydrogeologist that had been “provided to all ERC Members”. This so-called report is in fact a seven-page letter. It begins with the words: “This letter…”
Being only seven pages long, it goes nowhere near satisfying any criteria by which the word “report” is usually judged and quite naturally recommends “further work”. (Fortunately these recommendations were “accepted by AGD”. Phew! At least the mine’s happy!) The hydrogeologist says that more work needs to be completed and Colin Thornton takes this as a greenlight to go ahead with the dewatering because apparently the hydrogeological investigations now require it… well, they would, by now, wouldn’t they? No use trying to discover the conditions prior to dewatering when the area had already been dewatered for two months against Planning Permit conditions. They may as well carry on mining, now, eh?

It should be noted again as extremely important that the Burns’ letter to which we refer here is actually merely a call for the submission of a proposal; it is NOT a commission at all. 

AGD Operations Pty Ltd requires the services of a hydrogeological consultant and invites URS Australia Pty Ltd to submit a proposal for the provision of those services.

Yet, this is the evidence of the commissioning of a hydrogeologist that was presented by the mine to the ERC and was accepted by the regulators as fulfilling Permit conditions, as we shall see in what follows below.

Can we see the commissioning documents?
***
(In an interesting aside regarding matters that will be referred to elsewhere – the extent of the mine’s “zone of impact” or “cone of depression” – consider the information contained in this Work Plan Variation to the Open Cut Permit for ML 4644:

WPV February 2005
7.6 Groundwater Environment

The potential impacts on the groundwater environment include contamination by way of discharge of contaminated water to the groundwater and a lowering of the water table impacting on groundwater users.

The only potential source of contaminated water entering the groundwater is by way of seepage from the evaporation pond. The only variation described here that has the potential to influence seepage from the evaporation pond is the use of a geomembrane liner which reduces the potential for such seepage.

A detailed search of the records for the Costerfield area revealed no registered bores, other than those drilled by AGD for mineral exploration purposes, within 2000 metres of the site. This is not surprising when the quality of the groundwater, which makes it unsuitable for the majority of potential uses, is considered.

The results of hydrogeological studies into the impact of mine dewatering on water table levels indicate that a cone of depression with a radius of 1000 metres will be produced. [Emphasis added.]

So in February of 2005, the cone of depression – the impact of the mine’s dewatering – was estimated to have the potential to extend 1000 metres. Yet in his letter to Bryan Chadwick of 6 July, 2005, regarding the underground mine, Colin Burns states the “zone of impact” to now be 1500 metres.

No mention is made in the Permit governing the Underground Mine of the extent of the potential cone of depression. It’s getting bigger and bigger without comment from the Regulators.

We have also spoken in a previous submission of the relative (un)desirability of a geomembrane liner over a correctly prepared clay liner in order to “reduce the potential for seepage”, and the specific Permit requirements that the clay liner be constructed “to prevent seepage”. Here’s that “pond” again.

Is the use of a geomembrane liner really the “only variation described here that has the potential to influence seepage from the evaporation pond”? We would say definitely not, because the decision to use the clay liner as merely a base for holding the liner is in and of itself a variation that would potentially influence seepage.

There is no discussion as to why the clay liner was not constructed, but it is, of course, much easier and cheaper to install a plastic liner than to properly work the clay walls to specifications...
Oh and the reason no one in the area sank any bores in order to exercise their right to the amenity of groundwater use on their properties was because the creeks never ran completely dry and the groundwater “collection points” were usually wet. No one had much of a need for bores because there was always a usable quantity of groundwater available. 

People took fish out of the Wappentake Creek over Easter. 

And then dewatering began.)

***
To resume the discussion of the “commissioning” of the initial hydrogeological report.
Recall that the initial 18.5m drop in groundwater levels was “only indicative of what has happened during the preliminary stages of dewatering”. Certainly there was a drought. Still, Costerfield was spared much of the pain as it received around 75% of its usual rainfall over the period.

ERC Minutes April 2007
3. Minutes of Previous meeting

[Local landowner/farmer ERC Member] G*** suggested that the minutes circulated should be modified as follows:

a)     The record of his statement in regard to the length of time since water holes on his property were dry should be modified to state that those water holes are now dry for the first time since original selection of the land in the 1850s.

b)     That a record of his statement made at the meeting that Amelia O’Neil [URS] agreed with his view that water quality will change as it passes through the earth to the groundwater in the basement [aquifer].

It was moved by Bob Disken that the modifications suggested by G*** be made and that, given those modifications that the draft minutes be accepted as true record of the meeting. This motion was seconded by B*** and passed without dissent.

Business Arising

B*** stated that at no stage did he criticise the quality of the work performed in the hydrogeological investigation but he did believe that the scope of the investigations was too limited because it did not adequately cover issues of water quality. B*** further indicated that his interpretation of the Planning Permit condition and the contents of the approved work plan was that consideration of water quality issues was a definite requirement.

Colin Burns stated that such an interpretations [sic] of the permit condition and the contents of the approved work plan were wrong, and that water quality issues were not being considered because there is no suggestion that mine dewatering could impact on groundwater quality.

B*** stated that the use of piper plots was aimed at considering water quality issues.

Colin Burns stated that this view was wrong and that piper plots had been used to determine differences, if such differences exist, between water from various places, not to enable water quality assessment.

B*** stated that Amelia O’Neil, of URS, had advised him that URS had never been commissioned to conduct investigations aimed at determining whether a connection between surface water, alluvial aquifers and the basement aquifer exist.

Colin Burns stated that he found this very difficult to believe since the letter commissioning URS to undertake hydrogeological investigations included condition 24 of the Planning Permit, which clearly states that the commission is to “complete an investigation into the existence of a hydrogeological connection between groundwater in the arear of the mine and water collection points utilised on properties in the area as a source of water…”

Bob Disken reiterated the view of DPI that the hydrogeological investigations had been adequate, so far.

B*** stated that AGD were in breach of Planning permit condition 24.
Greg Speirs advised that this matter has been raised by B*** previously and referred to Dale Samson, the Council senior officer on mining matters, and the decision made was that Condition 24 was satisfied.

In his letter to Bryan Chadwick of URS in July of 2005, Burns had noted that “While there is some evidence, in terms of the water quality and the relative depths of the collection points and the groundwater…”. [Emphasis added.] So water quality was not a concept that was unfamiliar to him with regards AGD’s Costerfield Operations.  Yet here, he disavows any concern for consideration of the what he now deems to be "water quality" on the basis that AGD’s piper plots are supposed to measure “differences… between water from various places, not to enable water quality assessment”.

Differences in what? The chemistry of the water… that is, its quality.There's piper plots for you, in a nutshell.

(It should also be noted here that a "Water Quality Monitoring Program" was subsequently instigated at the site...)

Not only does this exchange reveal the acquiescence of the regulators to the verbal gymnastics of Burns, but it also indicates just how concerned the mine was about environmental conditions and the impacts its operations would have on its neighbours’ amenity. (The answer? Not very much at all!)  Piper plots can be, and usually are, readily employed to assess water quality, but that was not of concern to AGD. Or the regulators.

The hydrogeological investigations were “adequate, so far” apparently. Damned by faint praise from Bob.


 Can we see Dale Samson’s report to Council that accepts the request for an expression of interest as a commission?


No matter how you juggle it, a seven-page letter is not an initial hydrogeological report.



We no longer have any way of knowing what the conditions were in Costerfield prior to dewatering for the mine. Any conclusions drawn about the impact of the mine over the past decade are, in effect, speculative, given the scientific uncertainty regarding any initial baseline assessment.


The 7-Page Letter

This seven-page letter (1.2MB pdf), is NOT a hydrogeological report by any stretch of the imagination. (Here's the EPA's 1999 opinion on how these things should be done. Is it really good enough to sit at a desk and assess these things?)

It is a letter. It even calls itself a letter. A letter whose "Subject" is Initial Hydrogeological Investigations. Think of an email... Not a report. Its supposed place in the chronology of events is contradicted by its contents. And URS were not commissioned to complete an initial hydrogeological report in compliance with Permit Condition 24; they were commissioned to provide hydrogeological advice. 

Can we see the commissioning document?

These and many more issues will be raised and elaborated upon on this page in coming installments. 

In the meantime, please do familiarise yourself with the letter's contents. There's not too much to take in.

And also please consider the issues below.
 
This so-called report by URS (Letter 16/12/2005, Project No. 43270625.05005) had as its “main objective” merely “to summarise the information collected to date in regard to the hydrogeological and hydrology and assess the impacts of dewatering of the Augusta deposit on the environment” [emphasis added]. No objective to actually conduct their own information-producing processes to discover contemporary conditions prior to dewatering. Just summarise others' findings.

The conclusion (if one can call it that) was that the “basement aquifer is at least partially confined”. 


What does “at least partially” mean? Twenty percent? Seventy percent?

Even ‘totally’ is covered by the phrase “at least partially”, is it not? 

But so is ‘barely’...

A sentence is basically meaningless when its negative imparts the same information. Please compare "at least partially confined" with its opposite, "at least partially unconfined". Can you spot the difference?

Meaningless uncertainty.

Oh and information collected revealed that the creeks in the area are all ephemeral. Except the Wappentake Creek. It flows most of the year. Keep this in mind for later discussion.

But the scientific uncertainty... 

And they went ahead and dewatered anyway.


Thursday, 25 September 2014

To The Minister 1




Dear Minister

We have just been made aware of this news article from the Bendigo Advertiser, dated 11 September, 2014, regarding the very gracious and productive visit paid to Costerfield by Ms Lily D’Ambrosio and Ms Clare Malcom on the previous day. It reads, in part:

Ms D'Ambrosio said the government's handling of the Costerfield disaster was reminiscent of the Hazelwood mine fire in Morwell.

"It's a repeated practice of the government of failing to respond in a timely fashion to community concerns," she said. 

"We need a government that shows leadership and that has not been forthcoming from Russell Northe or indeed the government as a whole," she said. 

Ms D'Ambrosio said Labor would formulate a plan for Costerfield before November in time for the election. 

A spokesperson for the state government said it was "laughable" and "a bit rich" for Ms D'Ambrosio to visit Costerfield six months after the community first made its concerns known.

"When a complaint was made regarding dust levels in March, this government responded immediately and directed the mine to put in measures to reduce the dust which are now in place and working effectively," the spokesperson said. 

"Ms D'Ambrosio is arriving six months late and her only purpose today is to spread fear and misinformation and it is despicable she would act so irresponsibly and without regard for the community.

The spokesperson said the Costerfield mine was approved, opened and operated under the previous Labor government. 

"Suggestions that an expansion of the Mandalay mine activities at Costerfield led to increased dust deposition levels are unfounded. 

"Mandalay Resources have not substantially changed their underground mining activities or production rates from the approvals granted in 2006 under the former Labor government."

It is quite obvious that this “spokesperson for the government” is not at all familiar with the progress of this mine. Have they been to Costerfield? Have you Minister? Also from the Bendigo Advertiser, dated 29 August, 2014, we have the following statement from Mandalay Resources’ General Manager, Mr Andre Booyzen:

Mr Booyzen said Costerfield Operations had now accessed all areas required for ore production for the 2014 financial year and early 2015 production.

"The mining rates towards the new Cuffley ore body were completed well in excess of anticipated rates," he said. [Emphasis added.]

And we also draw the Minister’s attention to a further Bendigo Advertiser article detailing the approval of the Splitters Creek Evaporative Facility (which is itself a reflection of the mine’s increased extractive operations) and titled, tellingly enough, “Bendigo mine expansion gets green light” from 24 June, 2014. [Emphasis added.]

So, according to the government, the mine has “not substantially changed their underground mining activities or production rates”? Indeed.

In light of this obvious misinformation (it's a lie really, isn't it?) from the unnamed “spokesperson for the government”:
  •    Will the Minister, please advise us as to how the “approvals granted in 2006 under the former Labor government” anticipated, and now accommodate, the expansion into the Cuffley Lode (let alone the previous expansions during the intervening years of Liberal government)? 
  •    Why, Minister, have environmental and health monitoring activities not been constantly revisited and updated to keep up with these incremental expansions that have taken place under the present government’s watch?
  •    Why, Minister, under the current government, has the regulation of this ever-expanding mine been allowed to continue, for eight years, without increased scrutiny or an improving of the standards of the environmental and health impacts? 
We don't think you or the government are listening to everything we are saying, Minister. 

At the Open Day organised by the government, the Chief Inspector of Mines attended in such an under-prepared state that he knew neither which way the creeks flowed with respect to the mine, nor the direction of the prevailing winds (we know why that is, don't we?). It wasn’t a very comfortable afternoon and evening for him, at all. And we were a bit embarrassed for him.

He was ignorant, too, of the fact that the mining license has still to be renewed by the Minister following its expiry. 

While both parties are to blame, Labor has at least decided to rectify all past and current problems in conjunction with the residents. The silence is deafening from the Other Side

If the Minister or his "spokesperson" had bothered to attend Costerfield with Ms D'Ambrosio and Ms Malcolm (in the spirit of bi-partisan concern for the community) they would have known that the matters under discussion were the need for an Environmental Effects Statement, the incremental expansion of the mine without due consideration of that expansion's full implications and the systematic under-regulation of the Costerfield Operations by this and previous governments.

Minister, surely it is time to stop playing politics and pointing fingers, and to, instead, start delivering some answers and solutions.

We thank both Ms D’Ambrisio and Ms Malcolm for attending Costerfield to hear our concerns, and look forward to having our voices heard during their preparation of a plan of action for the Costerfield mining operations in the very near future.

***
Apparently, "Departmental staff have also been and remain available to residents at any time to discuss any ongoing concerns". We have been asking questions for quite a while here now and have yet to receive any answers we can share. 

We still await your own reply to our previous questions. All of them.


Regards


The Wappentake Valley Community